Vestolit, an Orbia company, was evaluating a potential expansion of its Cartagena, Colombia facility. The project was in FEL-2, a stage focused on developing scope definition and authorization readiness. As part of Orbia’s broader transformation, Vestolit had recently centralized major project delivery under a corporate-led project model.
This shift created integration challenges:
Replicable Model: The governance and integration practices established in Cartagena were recognized internally as a model for future corporate-led projects.
This project demonstrated how strong FEL-2 discipline and organizational integration can de-risk authorization decisions. While the Project Director retained ownership of delivery, BPMP’s embedded support ensured smoother collaboration across countries and functions, proving that governance clarity and people-first leadership can accelerate project readiness.
Planning an expansion or modernization? Strengthen your FEL-2 package with governance clarity and team integration that accelerates authorization readiness.
Capital Decision Readiness References (FEL 2–3)
Reference checklists used to support FEL and capex decisions.
(from The Industrial Capital Project Playbook)